Customer


 

Scope of works


Maintenance to the inner and outer copings of the weir plates on 4 circular FSTs. The challenge was to avoid the time consuming and expensive task of draining and scaffolding the tanks.

 

Solution


Access extension from the wall and an external step provided ramp access. Rope and stanchion and Combisafe edge provided a totally safe bespoke solution . Installation time was 1/2 day. Works were completed without the need to drain and the pontoon solution was 40% lower than the scaffold quote.